"D3" Dead Dying Diseased Oak Tree Mortality & Fuels Reduction Program"

“D3” PROGRAM STATISTICS

Program Totals*
*as of March 31, 2010 – additional site evaluations still need to be completed

294 parcels enrolled
1,170 total acres
1,143 trees marked

“D3” PROGRAM PROCEDURE & ESTIMATEDTIMELINE
Updated May 25, 2010

The following is an estimated approximate program timeline and is subject to change at any time.

MAY – JUNE 2010
Archeological Cultural Resources Survey
(approx. 6-8 weeks)

JUNE 2010
Contractor Pre-Qualification Process
**

JUNE – JULY 2010
Public Bidding & Award Contract (Project 1 only)


JULY – AUGUST 2010 Complete Site Evaluations & Tree Marking (Projects 2, 3 & 4)

JULY – OCTOBER 2010
Tree Removal – Project 1
(approx. 90 days)

Public Bidding, Contract Awards & Tree Removal for Projects 2, 3 & 4 will follow from
October 2010 thru August 2011

**The RCD’s Pre-Qualification Certification Application will be available by June 1, 2010.
Please contact Krista Burroughs, D3 Program-Contracts Coordinator at 619.749.4232 or krista.burroughs@rcdsandiego.org for more information

Downloads

  1. D3 Program Information Flyer (PDF)
  2. Current Project Area Map (PDF)
  3. The Live Oak News – “D3” Newsletter
    Fall 2009 (PDF)
    Spring 2010 (PDF)
  4. Latest News & Updates
    Voluntary Oak Wood Quarantine (PDF)
    D3 Program Update – Archeology Consultant, May 2010 (PDF)
    Contractor Pre-Qualification Application, June 2010 (PDF) Coming Soon!
  1. Goldspotted Oak Borer (GSOB) Information
    GSOB Updates & Reporting (http://groups.ucanr.org/gsob/)
    USFS Wanted Poster (PDF)
 
   
2011-2012 San Diego Forest Area Safety Taskforce©